Automatic Traction Continue Casting Machine 350 Kwh/Ton For Copper Bar
1. main parameter
No. | Item | Data |
1 | Model No. | |
2 | Annual capacity | 3000tons |
3 | Casting Strands | 3 |
4 | Casting rod diameter: | 200*10mm |
5 | Upward casting speed | 0150mm/min |
6 | Annual working time | 7920h |
7 | Liquid tracking precision | ±2mm |
8 | Take-up standard | coiling |
9 | Copper melting velocity | 760kg/h |
10 | Copper melting power consumption | <350kwh/ton |
11 | Take-up form | automatic adjust |
12 | Take-up plate driven approach | inverter motor, PLC control |
13 | Material feeding method | whole piece of electrolytic copper cathode fed by electric hoist |
14 | Upward driven approach | driven by the AC servo motor, transmission chain is driven by the gapless synchronous cog blet |
15 | Rod clamping method | air clamping |
The continuous casting machine is the main part to realize the continuous up-casting which includes the traction system, the level tracking system and the crystallizer, the structure is gantry four pillar.
The traction system includes two units of servo motor, reducer and traction rolling wheel, it could make 0-600 times high speed interval motion and make the copper rod come up though the traction rolling wheel, each unit of traction system could drive 5 pair traction rolling wheel, and drag3 pcs copper rod separately.
The automatic level track system could insure that the crystallizer is in the stable depth in the copper liquid, and to make sure the producing is continuously.
The crystallizer could freeze the copper quick into solid-state by cooling it and realize the heat exchange, each crystallizer can be change and be controlled separately without any influence of other crystallizers’ normal working.