Place of Origin: | Zhejiang |
---|
Location: | Beijing, China (Mainland) |
---|---|
Business Type: | Manufacturer |
Main Products: | Frame Scaffolding System, Ring Lock Scaffolding System, Cuplock Scaffolding System |
Model No.: | 65 systerm |
---|
Aluminum Formwork / Aluminum Panels for construction
Gowe Group:
ZhengXin,as a member of GOWE Group, a collection of R&D ,manufacturing,marketing development and sales,leasing,service, as one of the environmental friendly enterprise organized by industry veteran, is specialized in new type formwork design and implementation.
The promoters of the company promote the Green Construction for more than 20 years, made an outstanding contribution in the green recycling using of Chinese infrastructure materials and they led the team to create “Liandong formwork company”, “GoWe Company”, two the company product conforms to the requirement of the time, and a leading domestic and even overseas market in different periods.
Professional management team, strong technical force is the basis of ZhengXin; “positive contribute to bonum, sincerity result in far-reaching” is the life fundamental of ZhengXin. On the construction of green environmental protection, for the construction more safety, more beautiful environment, more perfect quality is the new pursuit and mission; we look forward to people who are actuated by high ideals, common progress to realize the industry a bright future.
Products Advantages:
1. High efficience and short period for construction
Aluminum formwork adopt quick assembly and dismantling system. One floor can be finished only for 3-4 days, efficiently reduce ur labour cost and construction period cost.
2. High utilization for Recyclng---Average usage is 300 times
3. Easy to learn for workers
each worker can know how to assemble them through the instructions. One day 30 Sqm for each worker.
4.Safe for construction process and big bearing duty
5. Perfect walls surface, smooth and beautiful.
6. Accuracy and practicability
All construction can be finished though CAD and structural drawings-designing confirming-designing for further confirmed-designing completed.
7. Rerecovery value--After regard as useless, can be recycled again and again, thus can reduce the environment and air pollution
1 | Easy to Handle |
2 | Unsurpassed construction speed |
3 | Good stability, high bearing capacity |
4 | High Concrete Pouring Rate |
5 | Great Recyclable Value |
6 | No construction waste |
Material cost (Included Support) |
$156-216/m2 |
$13--16/m2 |
Turnaround times |
300 times |
3-5times |
Assembling and dismantling labor cost |
$3.6-4.2/m² |
$4.2-4.7/m² |
Subtotal artificer materials |
$4.4-4.9/m² |
$7.5-8/m² |
Leveling the wall plastering labor cost |
$0.4/m² |
$2/m² |
Leveling the wall plastering material cost |
$0.3/m² |
$2.6/m² |
Economics |
20m²/day |
15m²/day |
Final economic indicators |
$5.9-6.4/m² |
$12-13/m² |
|
Products showing
Certificate: